Bishoftu International Airport

Our largest current earthworks, worked day and night with our own plant.
We are delivering earthworks package EWP2 at Bishoftu International Airport for Ethiopian Airlines Group, with China Communications Construction Company as main contractor and Dar Al-Handasah as consultant. The work covers bulk excavation, cut and fill, haulage and site formation across the airport platform.
We mobilised in January 2026, and the work runs on our own fleet and certified operators.








Bulk earthworks across an airport platform
An airport platform has to perform as one continuous piece of engineered ground, and everything built later relies on it. Our package moves material from cut to fill across the platform. Fill goes down in controlled layers against a specified material classification, moisture condition and compaction requirement, and each layer is tested before it is approved to take the next.
Our engineers have worked the ground conditions across the platform. Our surveyors hold the setting out and volume records for each area we complete, so measured volumes trace back to survey.
Working day and night inside the airport perimeter
Plant, supervisory staff, haul roads, water supply and site establishment are all in place within the airport perimeter. Excavators load tippers at the cuts, graders and rollers follow on the fill, and work continues under floodlights after dark.
Earthmoving at this scale raises dust, so we suppress it at working faces, haul roads and stockpiles. Crews gather for briefings before work starts, and only certified operators run heavy machinery.
What Bishoftu says about our civil works
Bishoftu shows why we own our fleet. Excavators, tippers, graders and rollers come from our own books and go back to our own workshop for maintenance, which keeps decisions about availability with the people responsible for the programme.
It is also a project that sits within a bigger team, working under China Communications Construction Company as main contractor with Dar Al-Handasah as consultant.