Generation has doubled in seven years

Ethiopia's next power programme is a grid programme. Installed capacity rose from 4,462 MW to 9,752 MW over seven years, according to figures Ethiopian Electric Power (EEP) gave in May 2026, and the priority is shifting to the wires that carry that power.

The largest single step was the Grand Ethiopian Renaissance Dam (GERD), inaugurated on 9 September 2025 with an installed capacity of 5,150 MW. Project summaries from the engineering consultant Tractebel describe a roller-compacted concrete main dam 145 metres high with a 1.8 km crest, a rockfill saddle dam 5.2 km long, and 13 Francis turbines in two powerhouses. On those numbers one plant accounts for more than half of national capacity, which changes how a grid has to be planned and operated.

The results show up in the accounts. For the first nine months of the 2025/26 fiscal year, EEP reported about 25,000 GWh of generation, 90.16 billion birr of revenue and $366 million of export earnings, $138 million more than a year earlier. Djibouti, Kenya and Tanzania are among the buyers.

Why the grid is now the constraint

The clearest statement of what comes next is Ethiopia's National Energy Compact, prepared under the Mission 300 initiative led by the World Bank and the African Development Bank. It sets out transmission growing from 20,390 km in 2025 to 30,000 km in 2030, transmission substations rising from 144 to 323, and the distribution network expanding from 179,000 km to 456,000 km. EEP put the high-voltage network at more than 21,000 km in May 2026, so the work is under way, with most of the distance still to cover.

Losses are the other half of the argument. The Compact records transmission losses of 6 per cent, distribution losses of 22 per cent and commercial losses of 10 per cent, and aims for 5.5, 13 and 4.5 per cent respectively. Every point recovered in distribution is energy already paid for at the dam that reaches a paying customer without a single new turbine. In a system where demand is reported to be growing between 12 per cent a year (Ministry of Water and Energy, 2026) and more than 20 per cent a year (EEP, 2026), that can be some of the cheapest capacity available.

Access depends on how you measure it

Three access figures circulate, and each is honest about something different. A 2025 energy access survey found 65 per cent of the population with at least one source of electricity, including off-grid solar. EEP cited about 54 per cent in May 2026. The World Bank's stricter Tier 1 and above measure stood at 44 per cent on preliminary 2025 data, which leaves about 71 million people without sufficient access.

The Compact targets 75 per cent by 2030, reaching more than 9.23 million additional households, with roughly 70 per cent of new access from the grid and 30 per cent from off-grid systems. The next National Electrification Program, reviewed in June 2026, aims at universal access by 2035. The World Bank's $424 million ASCENT programme, approved in July 2025 with a Danish grant, is designed to connect nearly six million people over five years, concentrating on households and towns near the medium-voltage network.

For the construction side of the industry, that means thousands of small jobs in place of a few very large ones: medium-voltage extensions, transformers, service connections and meters spread across towns and rural corridors.

What is on the build list

Generation has not stopped. The 1,800 MW Koysha hydropower project was reported at 77 per cent overall progress in August 2026, with first turbine operation scheduled for late 2028 and completion in 2029. The Compact also lists up to 70 MW of geothermal at Aluto, 300 MW of wind at Aysha and 325 MW of committed public solar, on the way to a target of up to 14,000 MW by 2030.

Regional links are the third strand. The 1,045 km, 500 kV high-voltage direct current line from Wolayta-Sodo to Suswa in Kenya has been in service since December 2022 and can carry up to 2,000 MW in either direction, according to the World Bank. Contracted sales to Kenya were reported in September 2026 to be rising to 400 MW from December 2026, and about 100 MW has been reaching Tanzania on a pilot basis until upgrades on the route are complete.

Private money is starting to appear in the wires. In February 2026 Gridworks, part of the UK's development finance institution, signed a joint development agreement with the Ministry of Finance and EEP for two lines worth about $400 million, described as Ethiopia's first privately financed transmission projects: 198 km at 400 kV between Hurso and Ayisha, and 206 km at 132 kV between Degehabur and Kebridehar.

Paying for it, and what it means for builders

The Compact puts the investment requirement above $9.6 billion by 2030, with $4.9 billion for distribution and access, and aims to mobilise $3.06 billion of private capital. It also commits both state utilities to reform plans aimed at full cost recovery by 2028 through phased tariff adjustments, with a targeted subsidy for vulnerable households. Lenders tend to read that tariff path as closely as they read the engineering.

Hydropower schemes also need a great deal of ordinary infrastructure around them: access roads, water, power and homes for the people who operate them for decades. That is the part of the sector we know first-hand. At GERD we have delivered VIP houses and are building employees' dwelling houses for Ethiopian Electric Power, and we are building employees' dwellings at Gilgel Gibe II. It is a modest part of a very large picture, and a reminder that a power system depends on many trades besides those in the turbine hall.