What design and build means

In a traditional arrangement, the client appoints a designer, the design is completed, and a contractor then builds it. Under design and build, the client sets out what it needs and one company carries both the design and the construction. If a drawing does not work on site, the company that drew it is the one that has to fix it.

For clients, the main attractions are a single point of responsibility, the chance to overlap design and construction, and buildability built into the drawings. The main demand on the client is a clear brief at the outset, because the contractor will design to it.

How we deliver design and build

Our Engineering Technical Services team carries design, building information modelling and contract administration, and issues drawings for construction. It is part of the company. Design, procurement, construction and commissioning sit within one organisation, so revisions are controlled at source and the site is not left waiting for an outside office.

Procurement follows the approved design. Shop drawings and material submittals go for approval ahead of the procurement long lead, and nothing is ordered before it is approved. What we do not make ourselves, we import directly or buy through authorised agreements with manufacturers, which helps when long-lead items need early decisions.

Three examples from our own work

The employees' dwelling houses at the Grand Ethiopian Renaissance Dam are a design and build contract with Ethiopian Electric Power, under which we carry design responsibility for residential buildings and ancillary facilities at Guba, along with their roads, drainage, water supply and services.

The VIP houses at the same site were a design and build renovation of fifteen houses, including full luxury furnishing, site works and internal roads. Ethiopian Electric Power's letter records them as handed over in full compliance with the contract, the approved design and the quality standards.

At the Ethiopian Science Museum, we designed and built the permanent exhibition for the Ministry of Water and Energy. Here design meant more than drawings. It covered creative concept and storytelling, along with the exhibition architecture, interiors, lighting and services.

Keeping independent checks in a single-company model

A fair question about design and build is who checks the designer when the designer and the builder are the same company. We answer that through separation. Technical audit sits within our Enterprise Project Management Office and reports through its Deputy Chief Executive, outside the division building the work. Every stage has a gate, and the person who did the work cannot sign it.

Clients can also keep their own eyes on the project. We encourage a client's engineer or consultant to witness inspections and commissioning, and our inspection and test plans are agreed before work starts.

When design and build suits a project

Design and build tends to suit projects where speed matters, where the site is remote or awkward, or where the client wants one party to answer for the result. Housing at a hydropower scheme is a good example, because supply and logistics should shape the design from the start.

It suits less well where a client wants to control every design detail, or where a consultant is already appointed and the design is complete. We are comfortable there too. At the Ethiopian Artificial Intelligence Institute we are prime contractor with MAE Consulting and Architects as consultant, and we regularly coordinate with a consultant's design through shop drawings and submittals.

How a design and build project runs

Our sequence is the same for every project. Bill take-off, method statement and programme come before a price. On award we review the contract, put insurance and bonds in place, establish the site and issue a baseline programme within fourteen days. Design, procurement and construction follow, with weekly look-aheads and monthly valuations.

Systems are tested, balanced and demonstrated before handover. A joint inspection, written snag list and close-out certificate follow, along with as-built drawings and operation and maintenance manuals. A named contact then stays with the project through the defects liability period.

If you are weighing up procurement routes for a building, settlement or industrial facility, we are glad to talk it through at an early stage, when the choices are widest.