How big the sector is

Construction is one of the largest parts of the Ethiopian economy. Senior officials put it at 21 per cent of GDP in May 2024, and National Bank of Ethiopia data for 2021/22 showed it at 72 per cent of total industrial output and 42 per cent of operational investment projects. Those shares explain why a change in cement prices or foreign exchange rules travels so quickly through the wider economy.

The macro backdrop has been strong. The IMF's July 2026 review recorded real GDP growth of 9.2 per cent in 2024/25 and 7.8 per cent in 2025/26, with 8.2 per cent projected for 2026/27. Projections can move, and the IMF has also flagged higher fuel import costs as a pressure on the economy in 2026.

Where the work is

Energy remains the anchor. Ethiopia's National Energy Compact plans roughly 10,000 km of new transmission line and more than a doubling of the distribution network by 2030, alongside the 1,800 MW Koysha hydropower project, reported at 77 per cent progress in August 2026.

Aviation has the largest single job. Bishoftu International Airport, costed at $12.5 billion, began earthworks in January 2026, with a first phase planned by 2030.

Cities are the most widespread source of work. The corridor development programme, launched in Addis Ababa in 2024, was running in 75 cities across the regional states by March 2026, according to the Ministry of Urban and Infrastructure, which also counts about 2,500 cities and towns today against about 1,000 a decade ago. Each of those places needs roads, drainage, water and public space.

Housing is the deepest pool of demand. Addis Ababa's mayor told the city council in May 2026 that about 105,000 homes had been started through government funding and agreements with private developers, within a larger number under construction across all routes.

Public budgets are finishing what has started

The 2026/27 federal budget proposal totalled 2.34 trillion birr, of which close to 570 billion birr was for capital spending, 37 per cent more than the year before. The Reporter noted that the capital budget was shaped to exclude new major infrastructure projects, with 122 billion birr earmarked for finishing road projects already under way.

For contractors, the message is a useful one. Near-term public work is likely to favour completion of existing schemes, while the newest large projects are increasingly funded outside the federal budget. Bishoftu relies on airline equity and lenders. Power transmission is beginning to attract private developers. Housing is moving towards partnerships and mortgage finance. A contractor's order book now depends on understanding a wider range of clients and lenders than it did five years ago.

A new currency regime changed the arithmetic

The largest single change for the industry since 2024 is the move to a market-based exchange rate, alongside an IMF programme approved in July 2024. Inflation averaged 26.6 per cent in 2023/24, 16.0 per cent in 2024/25 and 11.7 per cent in 2025/26, with 12.3 per cent projected for 2026/27. Foreign exchange reserves rose from 0.7 months of imports to 2.1 months over the same period, and the IMF reported further steps towards an interbank market.

Better access to foreign currency helps importers of plant, steel and building systems. Prices, however, now move with the market, so a contract priced in birr carries a different kind of risk from the one it carried under a fixed rate. Price adjustment clauses, shorter bid validity and earlier procurement of imported items have all become more valuable, on both sides of the contract. Credit is shifting as well. The IMF's tables show private sector and state enterprise credit shrinking by 9.7 per cent in 2024/25, then growing by 55.9 per cent in 2025/26, a swing that developers and suppliers feel directly.

Rules, safety and who gets to compete

Regulation is moving towards tighter standards. A draft bill reported in September 2023 proposed making safety performance a main criterion in contractor pre-qualification, with a safety officer required on each site. Ministry directives reported in 2021 set out a framework for joint ventures between local and foreign contractors. Federal Procurement Proclamation 1333/2024 extended procurement rules to federally owned public enterprises, created a specialised appeals board and increased reliance on electronic systems.

The direction is broadly the same across all three: more documentation, more transparency and more weight on demonstrated capability. Firms with clear records on quality, safety and past performance stand to gain from that, and clients gain a better basis for comparing bids. The field is a wide one, with about 23,000 licensed contractors reported in 2021, and part of the stated aim of the joint venture framework was to help local firms take a larger role on major projects and gain from technology transfer.

What this looks like from a site

The pattern we see as a Grade One contractor is a market with plenty of work and less room for error. Large clients want partners who can carry several trades, and their lenders want evidence of plant, people and systems before a contract is signed. The firms that do well over the next few years are likely to be those that treat procurement, currency and safety as part of the engineering, and plan them with the same care as the concrete.