Cement: capacity has caught up
Cement is the material Ethiopia has come closest to mastering at home, while steel is where the import dependence remains. National cement capacity stood at about 20 million tonnes a year in May 2025, according to the Ministry of Mines, after an expansion at Dire Dawa added 0.6 million tonnes. The minister also pointed to four coal processing plants being commissioned, which matters because kiln fuel is one of the main inputs behind that capacity.
The largest recent addition is Lemi National Cement, with a reported capacity of 150,000 quintals a day, which is 15,000 tonnes. Its arrival coincided with a sharp price move. In January 2025 the Ministry of Trade and Regional Integration told Parliament that cement prices had halved from 2,200 birr to 1,100 birr per quintal after the plant entered the market and a previous directive was replaced.
Two cautions apply. Nameplate capacity is different from output, which depends on fuel, power and maintenance, and published figures for actual production vary. Prices also differ widely by region, because cement is heavy and costly to move. Delivered cost at a remote site can be a very different number from the factory price.
Steel: the import question
Steel is the opposite story. Reporting in November 2024 put national demand at about 5.3 million tonnes a year and imports in the preceding year at 1.25 million tonnes, worth about $600 million and mostly from China, a large jump on 201,000 tonnes the year before. Domestic manufacturers were reported in 2023 to produce about 2 million tonnes a year, with members of the sector's industry association running at around 20 per cent of capacity.
The explanation lies upstream. Ethiopian mills roll and fabricate, but they rely on imported billet and limited domestic scrap, so their output depends on foreign exchange and shipping as much as on demand. Producers cited shortages of foreign currency allocation and scrap as key limits in 2023. Rebar from one plant was reported at a factory-gate price of 120 birr a kilogram that year, which gives a sense of how exposed the input is to the exchange rate. Demand swings too: one mill reported sales down about 60 per cent over two years in 2023, as large public housing projects paused.
Authorities have tightened how imported steel is handled. In late 2024, customs began requiring importers using duty-free privileges to deposit cash equal to the duty until legitimate use was verified. Industry concerns about informal imports, reported to be about 15 per cent cheaper in 2023, were part of that discussion. For buyers, quality assurance and mill certificates have become a basic discipline.
Finishes and the import substitution push
Government policy favours making more at home. The Ministry of Industry identified around 96 products for substitution within a decade, with construction materials among the priorities, according to a July 2024 report. Ceramics show what that can look like. A tile plant at Mojo inaugurated in May 2026 represents an investment of more than 2 billion birr and sources about 80 per cent of its raw materials within 100 km, according to the Ethiopian News Agency.
Other categories remain mixed. Architectural glass, aluminium profile, lifts, pumps and much electromechanical plant are still commonly bought from abroad or assembled from imported parts. Each is a candidate for local value-add, and each needs enough stable demand to justify the investment.
Currency and logistics set the price
Two forces sit behind almost every imported material. The first is the exchange rate. Since the market-based regime began in 2024, access to foreign currency has widened, and import prices move with the market. The IMF projected average inflation of 12.3 per cent for 2026/27, so price risk remains part of any multi-year contract.
The second is the corridor. A 2023 logistics survey noted that the Addis Ababa to Djibouti route handles about 95 per cent of Ethiopia's trade. A landlocked economy feels every delay at the port or on the road in its site programmes, particularly for steel and for long-lead equipment. Large schemes are not immune. Reporting on the Koysha hydropower project in 2026 noted foreign exchange pressure on financing, even as its electromechanical equipment was being made in factories abroad.
Bulk materials follow a different logic. Aggregate, sand and block are heavy and low in value, so haulage quickly dominates their price. That favours local quarries, on-site batching and regional supply, and it is why large projects often establish their own crushing and concrete production.
How to plan around it
Four habits help. Split the bill of quantities early into local, mixed and imported items, so that risk is priced where it sits. Place long-lead orders early and agree how currency moves are shared. Test everything, because a certificate from a reputable mill costs little beside a failed pour. And wherever volumes justify it, shorten the chain by producing close to the work.
That last point has shaped our own direction. We run precast production for our own works, we are developing our metal manufacturing plant at Sendafa, and we hold a large-scale basalt licence at Keta Ejersa that is being developed to supply aggregate. Moving towards making more of what we once bought is a way of managing the same risks every contractor in Ethiopia faces.